Environmental Clearence
* The Environmental Impact Assessment(EIA) Studies for the Project was done by M/s BS_Envitech (P) Ltd.
* Presentation TOR for conducting EIA was cleared by MoEF on 15th Dec 2008.
* The company has got final clearance from MoEF on 15/07/2009.
* Public hearing for the project was completed on 4th March 2009.

Water
Sea water permission for withdrawal to the tune of 150 cusecs for the total capacity of 1980 MW has been received from Government of Andhra Prdesh and desalinated water will be supplied by Krishnapatnam port company for the project.
The requirement of water for the two stages of the Plant will be as follows:
Description stage-1 stages- 1&2
Total Sea Water requirement(cmh) 8070 12105
Total in cusecs 79.2 118.8
CRZ Demarcation Studies
CRZ (Coastal Regulation Zone) demarcation has been carried out by National Institute of Oceanography(NIO) and approval/clearence is obtained.

Long term open Access
Application filed with PGCIL for Long Term Open Access(LTOA) on september 28, 2008. 

Mega power Status
Qualified for Mega power project status and thereby is entitled to all the applicable benefits such as exemption from customs duty, tax holiday for 10 years etc.

Power Offtake
Discussions initiated with major bulk power trading agencies.

Other statutory Clearance
* NOC from Airport Authority: Application filed with Airport Authority of India (AAI) for approval.
* Forest Clearance: The Company has received clearance from Chief Conservator of Forests, Government of Andhra Pradesh.
* Defence Clearance: The Company has received approval from Ministry of Defence.

Clean development Machanism
project with super critical technology being qualified, it can be registered as a CDM project with UNFCCC at appropriate time.
This will enable generation of additional revenue over and above the sale of Power, by selling the Certified Emission Reduction(CERs) to any Emission Compliance buyers from developed countries. 

 
News & Events
Corporate Profile Services Environmental Clearence
The project is planned to be completed in two stages. The first Stage two 1320Mw (2x 660 MW)is under implementation. To undertake or carry on the business of cunsultancy or management of the whole of the affairs of the company or firm or any part of the assets of a company or firm with similar or different objects. The Environmental Impact Assessment(EIA) Studies for the Project was done by M/s BS_Envitech (P) Ltd.